Venue
Stamford AFC, home of The Daniels
Timescale
3-4 weeks
Brief
- Design and install a standalone toilet block to accommodate spectators
- Hard wearing fittings
- Maintenance considerations
- Aesthetically considerate to the local area of Stamford using natural materials
- Simple internal design with easy cleaning surfaces
Specification
- Timber clad finish
- Stainless steel urinal trough
- Secure access
- Concealed cisterns and pipe work where possible • Compact Grade Laminate (CGL, aka SGL) panels for cubicles
- Heavy duty cubicle fittings
- Wall hung basins with single pillar mixer taps • Concrete floor dust sealed
Design
- Choice of natural materials to clad the building
- Hard wearing fittings
- Security access gate
- Service void for cisterns and pipe work for ease of maintenance
- Insulated walls and ceilings for improved building efficiency
- Paintedfloor
- Polycarbonate safety mirrors
Installation
- Fabrication of structure in sections off-site for speed of insulation on-site
- Services were brought to an agreed point by main contractor and IGLOOS® connected all plumbing and electrics
- All crew CSCS qualified