Venue
Berry Hill High School, Stoke-on-Trent
Timescale
4 Weeks
Brief
By July 2011 the washrooms at the school were in a state of disrepair due to vandalism and neglect. As a result a number of the areas were closed. IGLOOS® won the contract to refurbish the washrooms within the tight deadline of the summer holidays.
Specification
- IgPS - IGLOOS® Plumbing Structure, was used extensively in the refurbishment
- Compact Grade Laminate was used in the cubicles and wall paneling. This is an ideal product for environments that undergo intensive cleaning and are subject to misuse
- Corian vanity units with a 10 year Du Pont guarantee replaced stainless steel vanity units
Design
- Durable and water resistant
- Bold colour scheme reflecting a contemporary feel
- Vandal resistant mirrors creating a more
- hospitable environment
Installation
- Quick and clean
- Installed during the summer holidays